Gilmer County Multi-Modal Transportation Study

Advisory Panel Meeting

Presentation Agenda

Team Members

Advisory Panel Role

Work Plan Activities

Schedule

Preliminary Findings

Growth *
Subdivisions Number Number of Units
Existing 117 2,810
Approved Minor (percent increase) 8 (7%) 36 (1%)
Approved Major (percent increase) 31 (26%) 1,086 (39%)
Total (percent increase) 156 (33%) 3,932 (40%)

* Growth will add 10,605 daily trips to the County's traffic.

MTPT Results
Level of Service Current Miles 2030 Miles
F 1 (0.2%) 63 (13%)
E 7 (1.5%) 16 (3.3%)
D 20 (4%) 26 (5.4%)
C or above 455 (94%) 378 (78%)
Total 483 (100%) 483 (100%)
System Preservation
Rating Good Fair Posted Closed Total
# of bridges (%) 47 (64%) 9 (12%) 16 (22%) 1 (1%) 73 (100%)
Multi-Modal
High Crash Locations
2001 - 2004
Potential Project Costs
Category Need Estimated Cost *
Capacity 40 miles $160,000,000
Operations Nine intersections $6,750,000
Bridge 26 bridges $19,500,000
Pavement 130 miles $26,000,000
Sidewalk Four miles $2,800,000
Bicycle Five miles $750,000
Total   $215,800,000

* ROW costs not included

Other Studies Ongoing

Potential Intersection/Roadway Issues

Other Issues

Public Involvement Activities

Study Results